Initially, activate the first product with the key combination Ctrl + shift + 1.
The Worker Gantt shows that the workers at Station_02 and Station_03 cannot complete their specified processes in the specified cycle time. The process that goes beyond the cycle time is called "Abdeckung an Fahrwerk". Move this process in a logical way to relieve the workers.
For a better overview, activate "show enhanced options" and "Show only active product" to display only one product at a time. “Auto-Recalculate" recalculates the worker paths each time the process changes. If you would like to recalculate the worker paths afterwards, this is done via Alt + Shift + R or recalc
It is important to make sure that the processes that were previously carried out by the operator on the left side are still carried out on the left side after the process shift. This also applies to the processes on the right side. In addition, these changes must be made for all three products. (ctrl + shift + 1/2/3)
In order for the software to display this processing correctly, a final step must be taken after the processes have been moved. With the help of the Table Editor, the "Count" is first changed to any number and then reset to one. Now at Station_04 there should be two boxes with covers on each side.
The placement of the materials at Station_02 and Station_03 should also be improved. The aim is to place the materials as shown on the right side of the screenshot. After moving the processes, correct this using the Material Zone Editor.
Save your progress with the button in the upper right corner of the screen.